07-09-19 Streets Project Update – TENTATIVE Timeline

North, South and Level Streets Residents here is a TENTATIVE timeline of the streets project that is currently being done in the Village:


  1. July 10th and 11th, Wednesday and Thursday, contractors will be doing stringlining for the new curb and gutters.
  2. July 12th or 15th, Friday or Monday, concrete contractor will be pouring the new curb and gutters. Once poured, you will NOT be able to drive on the concrete for 7 days while it cures. You will be able to park in front of you homes, on the gravel, just do NOT drive on the curb and gutter or over it to get in your driveways.
  3. July 16th or 17th, Tuesday or Wednesday,  the flatwork concrete contractor will come in to do the flatwork (pouring driveways to replace any that were torn out during construction).
  4. July 18th or 19th, Thursday or Friday, paving of asphalt will be done.

NOTE: THESE ARE TENTATIVE DATES AND ARE SUBJECT TO CHANGE


Once all of the above is done, the contractor will relocate to Farwell and Weaver Streets.