07-23-19 Project Updates

The following project updates were just provided for completed work done the week of July 15th
& anticipated work to complete the week of July 22nd.

Cardinal Way:

Completed the week of July 15, 2019

  1. Excavated Cardinal Way to subgrade.
  2. Conducted proof roll on subgrade.
  3. Completed pressure test on water main.
  4. Clearing and grubbing on the south side of the Project.

Anticipated schedule for the week of July 22, 2019

  1. Contractor to provide ditch checks along C.T.H. ‘HHH’
  2. Contractor waiting for the gas company to install utility.  The gas company is scheduled to be on-site August 2, 2019.

 

Proposed 2019 Infrastructure Improvements’ Project (Level Street, South Street, and North Street)

Completed the week of July 15, 2019

  1. Augelli Concrete installed concrete curb and gutter.
  2. Augelli Concrete installed all flatwork (concrete driveways and concrete sidewalks)
  3. Owen’s Excavating provided gravel for street preparation.

Anticipated schedule for the week of July 22, 2019

  1. Iverson Construction scheduled to be on-site Monday (7/22/19) and Tuesday (7/23/19) to finish grading of gravel.
  2. Iverson Construction scheduled to be on-site Wednesday (7/24/19) to provide hot mix asphalt. UPDATE: Monday, (7/29/19)
  3. Owen’s Excavating to provide landscaping behind concrete curb and gutter.

NOTE: with construction there is always a possibility of date changes.