Cardinal Way:

Completed the week of July 22, 2019

  1. Contractor provided sod at Mr. Tallman’s residence.
  2. Delta 3 Engineering provided lathe for the subdivision lot corners for installation of private utilities.
  3. Safe sample on water main passed and copy from laboratory sent to Village and engineer.
  4. Not much else this week.  Contractor waiting for the gas company to install utility.  The gas company is scheduled to be on-site August 2, 2019.

Anticipated schedule for the week of July 29, 2019

  1. Gas company to install utility late in the week.

Proposed 2019 Infrastructure Improvements’ Project (Level Street, South Street, and North Street):

  1. Iverson Construction finished grading of gravel.
  2. Owen’s Excavating adjusted all water valves and sanitary sewer manholes to finished grade.
  3. Iverson Construction installing binder course of hot mix asphalt tomorrow (Saturday, July 27th)

Anticipated schedule for the week of July 29, 2019

  1. Iverson Construction to install surface course of hot mix asphalt on Wednesday, July 31.
  2. Owen’s Excavating to provide landscaping behind concrete curb and gutter.