08-05-19 Streets and Subdivision Project Updates

Delta 3 Engineering Progress Report for Ridgeway Projects

Cardinal Way:

Completed the week of July 29, 2019

  1. Contractor installed water service to Lot #12.
  2. Gas company completed installation of utility.
  3. Alliant Energy on site working on the poles at the 3 Phase.
  4. Contractor started breaker run and gravel installation on Cardinal Way.

Anticipated schedule for the week of August 5, 2019

  1. Contractor to complete breaker run and gravel installation on Cardinal Way.
  2. Alliant Energy installing 3 phase main line.
  3. Augelli Concrete to pour concrete curb and gutter on Tuesday or Wednesday.
  4. Final street preparation.

Proposed 2019 Infrastructure Improvements’ Project (Level Street, South Street, and North Street):

Completed the week of July 29, 2019

  1. Iverson Construction provided surface course of hot mix asphalt.

Anticipated schedule for the week of August 5, 2019

  1. Owen’s Excavating to provide landscaping behind concrete curb and gutter.
  2. Re-install mailboxes.
  3. Owen’s Excavating to move equipment, etc. over to the Farwell/Weaver portion of the project.