08-05-19 US Hwy 18-151 Project Update

1204-05-72 USH 18/151 Iowa County – Weekly Construction Update for week of August 5th

This week crews continued stage 2 of the project – base patching, and are working on asphalt paving the first lift for the westbound passing lane.

 

For the week of August 5th:

Work in the westbound lanes includes:

  • Left/Passing lane closed from Pikes Peak Road to the Ridgeview/CTH BB/CTH HHH Interchange in Ridgeway as well as E County Line to CTH ID:
    • Asphalt paving
    • Shoulder
    • Pavement marking

Traffic switch anticipated to Stage 3 in the morning of August 6th:

  • Right/Driving lane closed from E County Line to CTH ID
    • Work on the bridge over S. Jones Street
    • Sawing for base patching
    • Base patching
  • Right/Driving Lane closed from Pikes Peak Road to the Ridgeview/CTH BB/CTH HHH Interchange in Ridgeway
    • Sawing for base patching
    • Base patching

For more information, please visit the project website:

https://projects.511wi.gov/us18151/