08-13-19 Update Cardinal Way Subdivision

Things are moving along very nicely with the new Cardinal Way Subdivision!

Completed the week of August 5, 2019

  1. Contractor completed breaker run and gravel installation on Cardinal Way.
  2. Augelli Concrete installed concrete curb and gutter.
  3. Alliant Energy on site installing power poles.
  4. Contractor final grading for concrete sidewalk.
  5. Concrete sidewalk will be installed Friday, August 9, 2019.

 

Anticipated schedule for the week of August 12, 2019

  1. Alliant Energy installing 3 phase main line near the Cardinal Way entrance on Tuesday and Wednesday.
  2. Alliant Energy installing utility in the subdivision on Thursday.
  3. Final street preparation.
  4. Iverson Construction possibly on site late in the week to install hot mix asphalt.  I will keep everybody posted during the week.
  5. Close on lots 3 and 5.
  6. Builder to start digging foundations Monday.