08-19-19 Delta 3 Streets/Infrastructure Project Update

Proposed 2019 Infrastructure Improvements’ ProjectNorth, South, Level, Farwell and Weaver Streets:

Completed the week of August 12, 2019

  1. Owen’s Excavating mobilized equipment, etc. to the other part of the Project (Farwell Street, N. Weaver Street, and S. Weaver Street).
  2. Owen’s Excavating provided traffic control and erosion control for the Farwell Street side of the Project.
  3. Owen’s Excavating installing sanitary sewer on Farwell Street.  Owen’s crew installed roughly 300’ of sanitary sewer and two (2) sanitary sewer manholes.

Anticipated schedule for the week of August 19, 2019

  1. Finish landscaping on Level Street, South Street, and North Street.
  2. Re-install mailboxes on Level Street, South Street, and North Street.
  3. Set up mailbox bank for the Farwell Street side of the Project.
  4. Continue sanitary sewer installation on Farwell Street and South Weaver Street.