10.23.2020 Cardinal Way Phase II Construction Update

Week of October 19-23, 2020

  • Street(s) preparation for curb and gutter.  Installed breaker run and gravel on streets.
  • Curb and gutter installation was completed
  • Pressure test on sanitary sewer
  • Sanitary sewer televising
  • Sidewalk preparation
  • Lots of clean up

Week of October 26-30, 2020

  • Monday and Tuesday – sidewalk installation
  • Wednesday and Thursday – final street(s) preparation
  • Friday – Binder course hot mix asphalt installation (weather permitting)
    • Surface course to be installed in the spring of 2021