Work completed the week of July 12, 2021:

  1. J.I. Construction installed traffic control and erosion control on Hughitt Street.
  2. J.I. Construction began water main installation on Hughitt Street.

Anticipated work to be completed the week of July 19, 2021:

  1. Continue water main installation on Hughitt Street.
  2. Tie-in water main on Hughitt Street and Wells Street on Wednesday.  Anticipated water main shut off on Wednesday (7-21-2021) from 8 am to 4 pm.  Affected residents will receive a flyer on Monday.
  3. Water main installation on the west end of Keane Street to begin.