Construction Update

Tasks completed the week of May 9, 2022:

  1. Water main installation on east alley.
  2. Water service installation on Kirby Street.
  3. Sanitary lateral installation on west alley.
  4. Pressure test and safe sample water main on east alley.

Anticipated schedule for the week of May 16, 2022:

  1. Water main and water services on east alley.
  2. Sanitary laterals and sewer main on east alley.

It is anticipated that all the utility installation will be completed in the next week or two.  Road construction/curb and gutter/asphalt is anticipated to be completed by the end of June.  Almost there!!