08-05-19 Streets and Subdivision Project Updates

Delta 3 Engineering Progress Report for Ridgeway Projects

Cardinal Way:

Completed the week of July 29, 2019

  1. Contractor installed water service to Lot #12.
  2. Gas company completed installation of utility.
  3. Alliant Energy on site working on the poles at the 3 Phase.
  4. Contractor started breaker run and gravel installation on Cardinal Way.

Anticipated schedule for the week of August 5, 2019

  1. Contractor to complete breaker run and gravel installation on Cardinal Way.
  2. Alliant Energy installing 3 phase main line.
  3. Augelli Concrete to pour concrete curb and gutter on Tuesday or Wednesday.
  4. Final street preparation.

Proposed 2019 Infrastructure Improvements’ Project (Level Street, South Street, and North Street):

Completed the week of July 29, 2019

  1. Iverson Construction provided surface course of hot mix asphalt.

Anticipated schedule for the week of August 5, 2019

  1. Owen’s Excavating to provide landscaping behind concrete curb and gutter.
  2. Re-install mailboxes.
  3. Owen’s Excavating to move equipment, etc. over to the Farwell/Weaver portion of the project.

08-05-19 US Hwy 18-151 Project Update

1204-05-72 USH 18/151 Iowa County – Weekly Construction Update for week of August 5th

This week crews continued stage 2 of the project – base patching, and are working on asphalt paving the first lift for the westbound passing lane.

 

For the week of August 5th:

Work in the westbound lanes includes:

  • Left/Passing lane closed from Pikes Peak Road to the Ridgeview/CTH BB/CTH HHH Interchange in Ridgeway as well as E County Line to CTH ID:
    • Asphalt paving
    • Shoulder
    • Pavement marking

Traffic switch anticipated to Stage 3 in the morning of August 6th:

  • Right/Driving lane closed from E County Line to CTH ID
    • Work on the bridge over S. Jones Street
    • Sawing for base patching
    • Base patching
  • Right/Driving Lane closed from Pikes Peak Road to the Ridgeview/CTH BB/CTH HHH Interchange in Ridgeway
    • Sawing for base patching
    • Base patching

For more information, please visit the project website:

https://projects.511wi.gov/us18151/


07-29-19 US 18-151 Project Update

This week crews continued stage 2 of the project – base patching, and work on the USH 18 westbound bridge over S. Jones Street (Barneveld).  

For the week of July 29th:

Work in the westbound lanes includes:

  • Left/Passing lane closed from CTH K to Pikes Peak
    • Base Patching and centerline repair
    • Work on approaches to the bridge over S. Jones Street
    • Asphalt paving
    • Shoulder
    • Pavement marking
  • Left/Passing lane closed from Pikes Peak Road to the Ridgeview/CTH BB/CTH HHH Interchange in Ridgeway anticipated mid/late in the week
    • Asphalt paving
    • Shoulder
    • Pavement marking
  • Left/passing lane closed from E County Line to CTH ID anticipated mid/late in the week
    • Asphalt paving
    • Shoulder
    • Pavement marking

These lane closures are going to move as the asphalt paving operation moves. The limits listed above are approximate, and will change as each day progresses.

For more information, please visit the project website:

https://projects.511wi.gov/us18151/


07-29-19 Delta 3 Engineering – Village Project Updates

Cardinal Way:

Completed the week of July 22, 2019

  1. Contractor provided sod at Mr. Tallman’s residence.
  2. Delta 3 Engineering provided lathe for the subdivision lot corners for installation of private utilities.
  3. Safe sample on water main passed and copy from laboratory sent to Village and engineer.
  4. Not much else this week.  Contractor waiting for the gas company to install utility.  The gas company is scheduled to be on-site August 2, 2019.

Anticipated schedule for the week of July 29, 2019

  1. Gas company to install utility late in the week.

Proposed 2019 Infrastructure Improvements’ Project (Level Street, South Street, and North Street):

  1. Iverson Construction finished grading of gravel.
  2. Owen’s Excavating adjusted all water valves and sanitary sewer manholes to finished grade.
  3. Iverson Construction installing binder course of hot mix asphalt tomorrow (Saturday, July 27th)

Anticipated schedule for the week of July 29, 2019

  1. Iverson Construction to install surface course of hot mix asphalt on Wednesday, July 31.
  2. Owen’s Excavating to provide landscaping behind concrete curb and gutter.

07-23-19 Project Updates

The following project updates were just provided for completed work done the week of July 15th
& anticipated work to complete the week of July 22nd.

Cardinal Way:

Completed the week of July 15, 2019

  1. Excavated Cardinal Way to subgrade.
  2. Conducted proof roll on subgrade.
  3. Completed pressure test on water main.
  4. Clearing and grubbing on the south side of the Project.

Anticipated schedule for the week of July 22, 2019

  1. Contractor to provide ditch checks along C.T.H. ‘HHH’
  2. Contractor waiting for the gas company to install utility.  The gas company is scheduled to be on-site August 2, 2019.

 

Proposed 2019 Infrastructure Improvements’ Project (Level Street, South Street, and North Street)

Completed the week of July 15, 2019

  1. Augelli Concrete installed concrete curb and gutter.
  2. Augelli Concrete installed all flatwork (concrete driveways and concrete sidewalks)
  3. Owen’s Excavating provided gravel for street preparation.

Anticipated schedule for the week of July 22, 2019

  1. Iverson Construction scheduled to be on-site Monday (7/22/19) and Tuesday (7/23/19) to finish grading of gravel.
  2. Iverson Construction scheduled to be on-site Wednesday (7/24/19) to provide hot mix asphalt. UPDATE: Monday, (7/29/19)
  3. Owen’s Excavating to provide landscaping behind concrete curb and gutter.

NOTE: with construction there is always a possibility of date changes.

 


07-23-19 Office Closed

The Village of Ridgeway office will be closed Wednesday, July 25th through Sunday, July 28th. The office will re-open on Monday, July 29th at 8:30 am.


07-18-19 USH 18/151 Iowa County – Weekly Construction Update for July 22nd-27th

This week crews continued stage 2 of the project – base patching, and work on the USH 18 westbound bridge over S. Jones Street.

For the week of July 22nd :

Work in the westbound lanes includes:

  • Left/Passing lane closed from east of CTH K to Pikes Peak Road
    • Work on approaches to the bridge over S. Jones Street
    • Sawing of pavement
    • Base patching and longitudinal joint repair

For more information, please visit the project website:

https://projects.511wi.gov/us18151/


07-17-19 Job Opening – Administrative Assistant

Applications are now being accepted for the position of part time Administrative Assistant for the Village of Ridgeway. Primary job duties involve clerical tasks as directed by the Clerk/Treasurer or Village Board. Duties to include utility billing, receipting, elections and reporting for municipal governments. A full job description will be available upon request.

 Submit Resumes in person or by mailing to:

Village of Ridgeway
113 Dougherty Ct
Ridgeway, WI  53582

Resumes can also be left in the drop box located in front of the Village Office.

DEADLINE TO SUBMIT RESUMES: JULY 31, 2019


07-16-19 Foggy Water – 2019 Streets Infrastructure Project

It has come to my attention that some of our residents may have their water coming out of some faucets looking “foggy” (see picture). This is nothing to be concerned about as it is only air in the lines. Most likely from the water having been off during the recent construction and new mains being installed. It will eventually clear up once the air is out of the lines. To get the air out quicker, you can turn on your faucets and let them run for a few minutes.

If you have any questions contact the Village Clerk at 608-924-5881 or the Public Works Director at 608-669-0977.


07-10-19 UPDATED streets project timeline

THIS IS AN UPDATE TO THE NOTICE POSTED JULY 9TH (dates have changed slightly)

North, South and Level Streets Residents here is a TENTATIVE timeline of the streets project that is currently being done in the Village:

  1. Friday and Monday, July 12th & 15th contractors will be doing stringlining for the new curb and gutters.
  2. Tuesday and Wednesday, July 16th & 17th the new curb and gutters will be poured.
  3. The day after the curb and gutter are poured,  the flatwork concrete contractor will come in to do the flatwork (pouring driveways to replace any that were torn out during construction).
  4. Once the concrete is poured, you will NOT be able to drive on it for 7 days.
  5. You will be able to park in front of you homes, on the gravel, just do NOT drive on the curb and gutter or your driveways.
  6. Monday July 22nd paving of asphalt will be done.

NOTE: THESE ARE TENTATIVE DATES AND ARE SUBJECT TO CHANGE


  • Once all of the above is done, the contractor will relocate to Farwell and Weaver Streets to begin work on that part of the project.

  • Landscaping crews will come in when all 5 streets are completed to do the necessary landscaping.

If you have any questions call the Village office at 608-924-5881