Job Opening – Streets & Parks

LTE FULL-TIME STREETS/PARKS WORKER

This is a temporary full-time position performing a variety of unskilled or semi-skilled maintenance work, operate a variety of small equipment, mowing of village property and snow plowing of village streets.

Applications/resumes accepted through 5pm on September 5th, 2019 by mail or in person at:

 

Village of Ridgeway

113 Dougherty Ct.

Ridgeway, WI 53582

 

Full job description available at the Village of Ridgeway office, upon request.


08-19-19 Cardinal Way Subdivision Project Update

The village closed and the builder started construction at Lots 3 and 5 with pouring of the foundations! To view the most recent video click here.

Completed the week of August 12, 2019

  1. Contractor working on final street preparation.
  2. Contractor working on deceleration/acceleration lanes.
  3. Alliant Energy installed 3 phase main line near the Cardinal Way entrance.
  4. Charter Communications on site installing utility near Cardinal Way entrance.  Charter is essentially working with Alliant for sharing the installation of their utility.

Anticipated schedule for the week of August 19, 2019

  1. Alliant Energy installing utility in the subdivision early next week.  Alliant Energy did not get as far as they projected this week due to wet conditions.
  2. Charter Communications on site installing utility in the subdivision.  Again, Charter is working with Alliant.
  3. Charter Communications – regarding the existing poles and the service along C.T.H. ‘HHH’, Charter will have an outage in the transfer of the utility.  Charter has to provide a 30 day notice because of all the municipalities affected (Area from Ridgeway to Cassville).  The existing Charter wire on the poles and the Charter service on the ‘mound’ at the intersection cannot be disturbed until after the 30 day notice.  Ultimately, this means the final landscaping and grading along ‘HHH’ will not be completed until after Charter is through.
  4. Final street preparation by Iverson Construction.
  5. Iverson Construction on site mid-to-late in the week to install hot mix asphalt.
  6. Contractor will be completing deceleration/acceleration lanes.
  7. Contractor will be working on final grading and landscaping following utility companies completing their installations.

 


08-13-19 Update Cardinal Way Subdivision

Things are moving along very nicely with the new Cardinal Way Subdivision!

Completed the week of August 5, 2019

  1. Contractor completed breaker run and gravel installation on Cardinal Way.
  2. Augelli Concrete installed concrete curb and gutter.
  3. Alliant Energy on site installing power poles.
  4. Contractor final grading for concrete sidewalk.
  5. Concrete sidewalk will be installed Friday, August 9, 2019.

 

Anticipated schedule for the week of August 12, 2019

  1. Alliant Energy installing 3 phase main line near the Cardinal Way entrance on Tuesday and Wednesday.
  2. Alliant Energy installing utility in the subdivision on Thursday.
  3. Final street preparation.
  4. Iverson Construction possibly on site late in the week to install hot mix asphalt.  I will keep everybody posted during the week.
  5. Close on lots 3 and 5.
  6. Builder to start digging foundations Monday.

07-17-19 Job Opening – Administrative Assistant

Applications are now being accepted for the position of part time Administrative Assistant for the Village of Ridgeway. Primary job duties involve clerical tasks as directed by the Clerk/Treasurer or Village Board. Duties to include utility billing, receipting, elections and reporting for municipal governments. A full job description will be available upon request.

 Submit Resumes in person or by mailing to:

Village of Ridgeway
113 Dougherty Ct
Ridgeway, WI  53582

Resumes can also be left in the drop box located in front of the Village Office.

DEADLINE TO SUBMIT RESUMES: JULY 31, 2019


06-03-19 Subdivision Infrastructure Construction

Construction is to begin this week to get the water, sewer and street in for the new subdivision. Construction will be on the west end of the village, near County Road H Nouth and Main Street. Be aware of construction equipment and workers as you are entering or leaving the Village.

Keep watching for updates on this project.

 


Election Results 4-2-19

VILLAGE OF RIDGEWAY
ELECTION RESULTS
April 2, 2019

RIDGEWAY VILLAGE PRESIDENT
Jon Steen                                      37
Tracy Peterson                                 12
Joe Salava                                            6
Rick Short                                            3
Michele Casper                                   2
Krista Durst                                         1
James Gardner                                   1
Mike Scheidegger                              1
Jenna Vinje                                          1
Christopher Wenzler                           1
Scattering                                              1

RIDGEWAY VILLAGE TRUSTEE
Michele Casper                              85
Julene Garner                                83
Mary Kay Baum                             63

Jon Steen                                          57
Scattering                                           7

VILLAGE OF RIDGEWAY CONTEST WINNERS
YOU MUST COMPLETE AN OATH OF OFFICE OR DECLINE, WITHIN 3 DAYS.

JUSTICE OF THE SUPREME COURT
Lisa Neubauer                              71
Brian Hagedorn                            56

COURT OF APPEALS JUDGE DISTRICT 4
Jennifer Nashold                  100

DODGEVILLE SCHOOL DISTRICT-East of Hwy 23
Michael Knoedler                 102

DODGEVILLE SCHOOL DISTRICT-City of Dodgeville
Mike Humke                         99

DODGEVILLE SCHOOL DISTRICT-At Large
Jessica Wieczorek                   71
Darin E. Nagel                         47


Keep Fire Hydrants Clear

 

Reminder:

If you have a fire hydrant on your property please remember to shovel it out.